Home \ International \ A Bauer BG 30 in the center of Munich
A Bauer BG 30 in the center of Munich
02/08/2022
Pubblicato da Redazione
Bauer Spezialtiefbau constructs excavation pit for office and commercial building in Munich’s Central Station district.
In the center of the Bavarian capital and directly adjacent to Munich Central Station a new commercial and office building is currently being constructed on a demolition site. Since April 2022, Bauer Spezialtiefbau GmbH has been constructing a retaining structure with a total of 298 piles using the double rotary drilling system (FoW) in the newly vacated site on behalf of PI Projekt Bayerstraße 25 GmbH & Co. KG, a joint venture of the companies Bauwens and Büschl as well as ehret+klein.
What makes this drilling method unique: the combination of fully cased drilling with an internal, continuous auger. “The piles reach up to a depth of 18 m below the surface and are being constructed with a diameter of 620 mm using a Bauer BG 30,” explains Nicolai Gügel, Site Manager for Bauer Spezialtiefbau GmbH. “The excavation pit itself is being excavated to a depth of roughly 10.5 m.” In addition, anchor work is being executed with up to seven strands in two layers – in part below the groundwater level as well – along with strut work.
For this work, the excavation pit level was lowered by roughly 1.5 m and an auxiliary retaining structure was installed with lightweight profiles and trench sheets. Another challenge with this project is that three subway tunnels run directly beneath the excavation pit, which is why it cannot be excavated completely or in a single operation. “For this reason, the workspace is divided into sections that are excavated successively in different phases and secured with pit sheeting,” says Nicolai Gügel in conclusion.
The main work of Bauer Spezialtiefbau GmbH is expected to be completed in November 2022; including all demolition measures, the project will last until January 2024.

Ultime notizie di Bauer Macchine Italia

Perforation
30/08/2023
Bauer Spezialtiefbau executes foundation works for the world’s largest monopile manufacturing facility for offshore wind
SeAH Wind Ltd. commissioned the Joint Venture between Bauer...

Perforation
26/07/2023
Bauer Resources constructs excavation pit with geothermally activated elements
Bauer Resources constructs excavation pit with geothermally...

Perforation
18/07/2023
Pilot project of Bauer Spezialtiefbau receives DGNB Certificate
Pilot project of Bauer Spezialtiefbau receives DGNB Certific...

Perforation
11/07/2023
Bauer Spezialtiefbau completes follow-up order on the Monte Grande dam
Bauer Fundaciones Dominicana S.R.L., the Dominican subsidiar...

Perforation
29/06/2023
“Next level” desanding with the Bauer BE 600-C
High throughput, fast assembly, digital operation with remot...

Perforation
23/06/2023
Bauer presents the new compact BCS 185 cutter system
Bauer has presented its new BCS 185 cutter system, which has...
Altri International

International
23/09/2023
Yanmar CE celebrates 55 years of mini excavator excellence
A pioneer of the concept in the late 1960s and still driving...

International
22/09/2023
Kobelco introduces the SK230SRLC-7 and SK270SR(N)LC-7 SR excavators
Kobelco Construction Machinery Europe B.V. (KCME) announces...

International
21/09/2023
Wirtgen: New cold milling machine W 150 F(i)
New Wirtgen cold milling machine W 150 F(i) for high milling...

International
21/09/2023
Perkins addresses evolving industry demands for improved fuel efficiency
Available in 2026, the new Perkins 2600 Series engine platfo...
International
20/09/2023
Jekko participates in the 2023 edition of GIS
The Jekko's mini crane manufacturer will attend and exhibit...

International
20/09/2023
Scholpp uses its new Tadano AC 4.080-1 to lift a bridge into place
The crane service provider Scholpp and the steel fabrication...