Home \ International \ A Bauer BG 30 in the center of Munich
A Bauer BG 30 in the center of Munich
02/08/2022
Pubblicato da Redazione
Bauer Spezialtiefbau constructs excavation pit for office and commercial building in Munich’s Central Station district.
In the center of the Bavarian capital and directly adjacent to Munich Central Station a new commercial and office building is currently being constructed on a demolition site. Since April 2022, Bauer Spezialtiefbau GmbH has been constructing a retaining structure with a total of 298 piles using the double rotary drilling system (FoW) in the newly vacated site on behalf of PI Projekt Bayerstraße 25 GmbH & Co. KG, a joint venture of the companies Bauwens and Büschl as well as ehret+klein.
What makes this drilling method unique: the combination of fully cased drilling with an internal, continuous auger. “The piles reach up to a depth of 18 m below the surface and are being constructed with a diameter of 620 mm using a Bauer BG 30,” explains Nicolai Gügel, Site Manager for Bauer Spezialtiefbau GmbH. “The excavation pit itself is being excavated to a depth of roughly 10.5 m.” In addition, anchor work is being executed with up to seven strands in two layers – in part below the groundwater level as well – along with strut work.
For this work, the excavation pit level was lowered by roughly 1.5 m and an auxiliary retaining structure was installed with lightweight profiles and trench sheets. Another challenge with this project is that three subway tunnels run directly beneath the excavation pit, which is why it cannot be excavated completely or in a single operation. “For this reason, the workspace is divided into sections that are excavated successively in different phases and secured with pit sheeting,” says Nicolai Gügel in conclusion.
The main work of Bauer Spezialtiefbau GmbH is expected to be completed in November 2022; including all demolition measures, the project will last until January 2024.
Ultime notizie di Bauer Macchine Italia
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
Perforation
30/08/2023
Bauer Spezialtiefbau executes foundation works for the world’s largest monopile manufacturing facility for offshore wind
SeAH Wind Ltd. commissioned the Joint Venture between Bauer...
Perforation
26/07/2023
Bauer Resources constructs excavation pit with geothermally activated elements
Bauer Resources constructs excavation pit with geothermally...
Altri International
International
25/04/2024
Genuine parts ensure articulated hauler quality and uptime
The importance of good quality, reliable parts when maintain...
International
25/04/2024
Steil takes delivery of new Tadano AC 6.300-1 all terrain crane
Steil takes delivery of new Tadano AC 6.300-1 all terrain cr...
International
24/04/2024
New Palfinger's TEC Heavy-Duty Cranes Set Standards in Power & Precision
The new Palfinger PK 1350 TEC and PK 1650 TEC heavy-duty cra...
International
24/04/2024
SSAB and Manitou Group agree on fossil-free steel
Manitou Group announces the signature of a letter of intent...
International
23/04/2024
Bauma Innovation Award: Kick-off 2 May 2024
On the occasion of bauma 2025, the leading associations of t...
International
23/04/2024
JCB expands Hydradig line-up with Plus and Pro models
JCB is meeting the needs of customers across every industry...