In the fall of 2016, drilling contractor PPI Chrobok S.A. installed two new gas pipelines in
In the fall of 2016, drilling contractor PPI Chrobok S.A. installed two new gas pipelines in Poland. The alignment runs along existing gas lines and through geologically challenging terrain. With the laying of the 700 and 464-meter-long pipelines, Herrenknecht's Direct Pipe technology was used in Poland for the first time.
With the construction of a new north-south pipeline connection, Poland is reacting to the increasing local demand for gas. Part of this network expansion is the “Czeszów-Wierzchowice Gas Pipeline Project” in the southwest of the country. So far, only HDD technology (Horizontal Directional Drilling) had been used for crossing rivers or roads during pipeline projects in Poland. Used for decades, the method has proved its worth for large numbers of boreholes, but it reaches its technical and economic limits in heterogeneous, non-stable grounds.
The sandy, sticky clay of the pipeline crossings in Wierzchowice and Czeszów presented the drilling crew with just such project conditions. Furthermore, the two alignments with lengths of 700 and 464 meters respectively run along existing gas lines. Uncontrolled deviations during the drilling process thus had to be avoided at all costs. In view of these requirements, for the first time main contractor PGNiG Technologies S.A. together with drilling contractor PPI Chrobok S.A. opted for the innovative Direct Pipe technology from Herrenknecht. This method combines the advantages of microtunnelling and HDD technology. In a single step the required borehole is created and the prefabricated pipe is simultaneously installed without a trench.
Thanks to the gyrocompass navigation system which allows for an exact steering of the TBM, the drilling crew precisely installed the two pipelines with an outer diameter of 1,047 millimeters underground in just 13 respectively 16 drilling days. In doing so, they safely crossed, among others, beneath an ecologically sensitive fish pond. The sticky ground that typically tends to cause blockages is not a barrier for the Direct Pipe method. Even at very high levels of friction resistance, the 500 tonnes of thrust provided by the Pipe Thruster in the launch shaft is more than enough. Despite the small overcut of only few centimeters, no damages were detected at the coating after the pipe laying.
Overall, a very positive conclusion was drawn after successful completion of the project. With daily best performances of 147 meters, Roland Kośka, Planning & Monitoring Manager for client GAZ-SYSTEM, summed it up as follows: “As a combination of HDD and microtunnelling, Direct Pipe overcomes their respective limitations which, to a large extent, are no longer obstacles to pipeline construction. This will also allow us to pursue new projects in the future and complete them economically, quickly and with minimal impact on the local infrastructure and environment”.
Ultime notizie di Herrenknecht
Perforation
18/03/2024
Herrenknecht: eight tunnel boring machines for the Brenner project
Seventh tunnel boring machine handed over for the record-bre...
Perforation
08/02/2024
Herrenknecht presents tunnel boring machine for Vienna
Herrenknecht is supplying a tunnel boring machine for tunnel...
03/05/2021
Advance record at the Brenner Base Tunnel
The miners in the Brenner Base Tunnel are pushing ahead rapi...
23/07/2020
Mighty breakthrough for Europe's biggest boring machine
Following the specifications of customer Pavimental, Herrenk...
17/01/2020
Herrenknecht: Suse, Sibylle, Wanda and Käthchen from Baden set a fast pace in Swabia
Mechanized tunnelling technology for efficient and environme...
25/10/2019
Federal Chancellor Dr. Angela Merkel in Schwanau
German Chancellor Dr. Angela Merkel visited Herrenknecht on...
Altri International
International
30/04/2024
JCB's new generation backhoes bring greater levels of versatility
JCB unveils a number of key improvements to its backhoe load...
International
29/04/2024
Wirtgen's global market launch: Rock Crusher WRC 240(i)
Rock Crusher WRC 240(i) is the new Wirtgen's specialist for...
International
29/04/2024
JCB updates X Series excavators with the launch of JCB UX
JCB has updated the interior of the X Series excavator opera...
International
26/04/2024
Digitalisation and sustainability at the Wirtgen Group's "Technology Days"
Digitalisation and sustainability were the focal points of t...
International
26/04/2024
SVAB launches the successor to the popoular joystick Grip L8
At this year’s edition of Intermat in Paris on April 24-27,...
International
25/04/2024
Genuine parts ensure articulated hauler quality and uptime
The importance of good quality, reliable parts when maintain...