Home \ International \ Herrenknecht: "Käthchen" achieves breakthrough
Herrenknecht: "Käthchen" achieves breakthrough
31/07/2018
Pubblicato da Redazione
The site crew working with tunnel boring machine "Käthchen" ("Katie") has completed the second tube of the Bossler tunnel.
The site crew working with tunnel boring machine “Käthchen” (“Katie”) has completed the second tube of the Bossler tunnel.
The breakthrough near Mühlhausen im Tale in Baden-Württemberg is another milestone in the construction of the Stuttgart-Wendlingen-Ulm railway line. The Bossler Tunnel is part of the Stuttgart-Ulm railway project and is expected to go into operation in 2022.
When “Käthchen” (Ø 11,340 mm) broke through the target wall, the Earth Pressure Balance Shield (EPB) had completed around 18,000 meters of tunnelling in the sandstone, limestone and claystone rock. The Herrenknecht tunnel boring machine (TBM) finished the second tube of the Bossler Tunnel in early June. Now the shell construction of the tubes in this section is completed. The railway tunnel is of great importance for the new Wendlingen-Ulm line and is expected to go into operation in 2022. Travel time on the Stuttgart-Ulm route will be almost halved. Ten million passengers a year will benefit from the railway project.
The second tube of the Bosslertunnel runs parallel to the first, which the team from ARGE ATA Tunnel Albaufstieg (Porr Deutschland GmbH, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch-und Tiefbau GmbH, Swietelsky Baugesellschaft mbH) had already completed in November 2016. The TBM "Käthchen" was then disassembled into its individual parts, transported back to the starting point and prepared for the launch of the second drive. From April 2017, the machine again worked its way continuously through the rock.
Construction of the two tubes was carried out differently than originally planned. After the preliminary geological analysis, the construction team had only intended to use “Käthchen” over a distance of about 2.8 kilometers. In the course of further exploration, however, the soil conditions turned out to be more favorable than expected. The TBM from Herrenknecht was thus able to excavate nearly 7.8 kilometers in the first tube and even 8.8 kilometers in the second tube – which is almost the entire tunnel distance. The work progressed extremely quickly.
From the beginning, “Käthchen” achieved top performances. In June 2015 already, two months after the start of the drive in the first tube, she reached the thousand meter mark. She was able to cover up to 38 meters per day and after advancing for six months had already excavated three kilometers – a strong performance on the part of the site crew. A total of 60,000 segments were installed in the Bossler Tunnel. They were manufactured in the purpose-built factory close to the Aichelberg tunnel portal.
The Albvorland Tunnel is also part of the new construction of the Wendlingen-Ulm railway line. The Herrenknecht tunnel boring machines “WANDA” and “Sibylle” (Ø 10,820 mm) are in operation there – so far they have excavated almost four kilometers of tunnel. As part of the Stuttgart 21 project, Herrenknecht tunnelling technology is also working on the Filder Tunnel. The Multi-mode TBM “SUSE” (Ø 10,820 mm) has already excavated over 10 kilometers of the tunnel route planned to connect the main station with the airport.
Ultime notizie di Herrenknecht
Perforation
18/03/2024
Herrenknecht: eight tunnel boring machines for the Brenner project
Seventh tunnel boring machine handed over for the record-bre...
Perforation
08/02/2024
Herrenknecht presents tunnel boring machine for Vienna
Herrenknecht is supplying a tunnel boring machine for tunnel...
03/05/2021
Advance record at the Brenner Base Tunnel
The miners in the Brenner Base Tunnel are pushing ahead rapi...
23/07/2020
Mighty breakthrough for Europe's biggest boring machine
Following the specifications of customer Pavimental, Herrenk...
17/01/2020
Herrenknecht: Suse, Sibylle, Wanda and Käthchen from Baden set a fast pace in Swabia
Mechanized tunnelling technology for efficient and environme...
25/10/2019
Federal Chancellor Dr. Angela Merkel in Schwanau
German Chancellor Dr. Angela Merkel visited Herrenknecht on...
Altri International
International
30/04/2024
JCB's new generation backhoes bring greater levels of versatility
JCB unveils a number of key improvements to its backhoe load...
International
29/04/2024
Wirtgen's global market launch: Rock Crusher WRC 240(i)
Rock Crusher WRC 240(i) is the new Wirtgen's specialist for...
International
29/04/2024
JCB updates X Series excavators with the launch of JCB UX
JCB has updated the interior of the X Series excavator opera...
International
26/04/2024
Digitalisation and sustainability at the Wirtgen Group's "Technology Days"
Digitalisation and sustainability were the focal points of t...
International
26/04/2024
SVAB launches the successor to the popoular joystick Grip L8
At this year’s edition of Intermat in Paris on April 24-27,...
International
25/04/2024
Genuine parts ensure articulated hauler quality and uptime
The importance of good quality, reliable parts when maintain...